CGRC · Question #136
Applying the first three steps in the RMF to legacy systems can be viewed in what way to determine if the necessary and sufficient security controls have been appropriately selected and allocated?…
The correct answer is C. Gap analysis. When applying the Risk Management Framework (RMF) to legacy systems, the process of assessing existing security controls against required controls to identify deficiencies is best described as a 'gap analysis.' This helps determine if current controls are sufficient.
Question
Applying the first three steps in the RMF to legacy systems can be viewed in what way to determine if the necessary and sufficient security controls have been appropriately selected and allocated? Response:
Options
- ASequential
- BLevel of effort
- CGap analysis
- DCommon control
How the community answered
(35 responses)- A9% (3)
- B3% (1)
- C83% (29)
- D6% (2)
Why each option
When applying the Risk Management Framework (RMF) to legacy systems, the process of assessing existing security controls against required controls to identify deficiencies is best described as a 'gap analysis.' This helps determine if current controls are sufficient.
While RMF steps are sequential, viewing the application to legacy systems as a whole specifically to determine control sufficiency is more about identifying discrepancies, not just following steps.
'Level of effort' refers to the amount of work required, not the analytical method for determining control sufficiency.
For legacy systems, applying the RMF's initial steps (categorize, select, implement) involves evaluating the current state of security against the desired or required state. A 'gap analysis' is the specific method used to identify differences or 'gaps' between what controls are currently in place and what controls are necessary and sufficient for the system's categorization, providing a roadmap for remediation.
'Common control' refers to a security control that is inherited by multiple information systems, not a method for assessing existing controls on a legacy system.
Concept tested: RMF Application to Legacy Systems - Gap Analysis
Source: https://csrc.nist.gov/glossary/term/gap_analysis