CGEIT · Question #180

An enterprise is contracting with an outsourcing partner for a long-term engagement. The BEST time for the enterprise to plan for the event of contract termination is when:

The correct answer is C. developing the initial contract. Planning for contract termination is best done during the initial contract development phase to proactively manage potential exits and transitions.

Submitted by cyberguy42· Apr 18, 2026Risk Optimization

Question

An enterprise is contracting with an outsourcing partner for a long-term engagement. The BEST time for the enterprise to plan for the event of contract termination is when:

Options

  • Aplanning for the contract as part of business continuity.
  • Bissues surface in the contractual relationship.
  • Cdeveloping the initial contract.
  • Deither party decides to terminate the contract.

How the community answered

(18 responses)
  • B
    6% (1)
  • C
    89% (16)
  • D
    6% (1)

Why each option

Planning for contract termination is best done during the initial contract development phase to proactively manage potential exits and transitions.

Aplanning for the contract as part of business continuity.

Planning for contract termination is a specific aspect of contract management, distinct from general business continuity planning, although it contributes to overall BCP.

Bissues surface in the contractual relationship.

Waiting for issues to surface before planning for termination is reactive and can lead to hurried, disorganized, and potentially costly exits due to lack of prior agreement.

Cdeveloping the initial contract.Correct

Developing the initial contract allows for proactive identification and agreement on exit strategies, data migration, intellectual property rights, and transition services before the engagement begins. This foresight minimizes disruption and potential disputes if the partnership ends, ensuring a smooth and controlled transition.

Deither party decides to terminate the contract.

Deciding to terminate implies the event is imminent, which is too late to effectively plan and negotiate the complex details of contract termination.

Concept tested: Outsourcing contract termination planning

Topics

#Contract Management#Outsourcing#Exit Strategy#Risk Mitigation