What is the PRIMARY objective of a rollback in the context of the change management process?
The correct answer is C. Restore the system to its last state before the change was made. In change management, a rollback (also called a back-out plan) is a pre-planned procedure to reverse a change and return the system to its known-good state prior to the change. This is critical when a change causes unexpected failures, outages, or degraded performance. It is a…
Question
What is the PRIMARY objective of a rollback in the context of the change management process?
Options
- AEstablish a minimum understood and acceptable level of security requirements
- BIdentify the required changes needed
- CRestore the system to its last state before the change was made
- DValidate the system change process
How the community answered
(32 responses)- B3% (1)
- C91% (29)
- D6% (2)
Explanation
In change management, a rollback (also called a back-out plan) is a pre-planned procedure to reverse a change and return the system to its known-good state prior to the change. This is critical when a change causes unexpected failures, outages, or degraded performance. It is a risk mitigation mechanism. The other options describe different parts of the change management lifecycle: establishing security baselines (A), identifying needed changes (B), and validating change processes (D) are separate activities that occur before or after the change itself.