Which of the following is an essential element of a business continuity plan related to human resources?

The correct answer is A. Training and awareness programs. The human resources component of a BCP ensures that employees know their roles and responsibilities during a disruption. Training and awareness programs prepare staff to execute continuity procedures correctly when an incident occurs. Without trained personnel, even a…

Business Continuity (BC), Disaster Recovery (DR) & Incident Response Concepts

Question

Which of the following is an essential element of a business continuity plan related to human resources?

Options

  • ATraining and awareness programs
  • BData backup and recovery procedures
  • CIntrusion detection system (IDS)
  • DPatch management process

How the community answered

(41 responses)
  • A
    88% (36)
  • B
    2% (1)
  • C
    7% (3)
  • D
    2% (1)

Explanation

The human resources component of a BCP ensures that employees know their roles and responsibilities during a disruption. Training and awareness programs prepare staff to execute continuity procedures correctly when an incident occurs. Without trained personnel, even a well-written BCP will fail in practice. Data backup and recovery (B) is an IT/technical component, an IDS (C) is a network security tool, and patch management (D) is an IT operations process - none of these are HR-related BCP elements.

Topics

#Business Continuity Planning#Human Resources#Training and Awareness#Organizational Resilience