Which of these is the PRIMARY objective of a Disaster Recovery Plan?

The correct answer is C. Restore company operation to the last-known reliable operation state. A Disaster Recovery Plan (DRP) is a plan for processing and restoring operations in the event of a significant hardware or software failure, or of the destruction of the organization's facilities. The primary goal of a DRP is to restore the business to the last-known reliable sta

Business Continuity (BC), Disaster Recovery (DR) & Incident Response (IR) Concepts

Question

Which of these is the PRIMARY objective of a Disaster Recovery Plan?

Options

  • AOutline a safe escape procedure for the organization's personnel
  • BMaintain crucial company operations in the event of a disaster
  • CRestore company operation to the last-known reliable operation state
  • DCommunicate to the responsible entities the damage caused to operations in the event of a

How the community answered

(28 responses)
  • B
    7% (2)
  • C
    89% (25)
  • D
    4% (1)

Explanation

A Disaster Recovery Plan (DRP) is a plan for processing and restoring operations in the event of a significant hardware or software failure, or of the destruction of the organization's facilities. The primary goal of a DRP is to restore the business to the last-known reliable state of operations (see Chapter 2 ISC2 Study Guide, module 4, under The Goal of Disaster Recovery). Maintaining crucial operations is the goal of the Business Continuity Plan (BCP). The remaining options may be included in a DRP, but are not its primary objective.

Topics

#Disaster Recovery#DRP Objectives#IT Systems Recovery

Community Discussion