New server equipment is arriving at your data centre, where should it be tested?

The correct answer is D. In the Staging room. New equipment should be unpacked, tested, and configured in a dedicated staging room before being moved to the live data hall to prevent contamination and disruptions.

Operational Aspects

Question

New server equipment is arriving at your data centre, where should it be tested?

Options

  • AIn the Holding area
  • BIn the Computer! Server room
  • CIn the Media storage area
  • DIn the Staging room

How the community answered

(42 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    5% (2)
  • D
    90% (38)

Explanation

New equipment should be unpacked, tested, and configured in a dedicated staging room before being moved to the live data hall to prevent contamination and disruptions.