The technical manager in an imaging/document management company is responsible for all aspects of the client's system installation. What are three things that will ensure all installations are…

The correct answer is C. A written implementation plan, design reviews, post-implementation review. See the full explanation below for the reasoning.

Question

The technical manager in an imaging/document management company is responsible for all aspects of the client's system installation. What are three things that will ensure all installations are completed in a consistent manner?

Options

  • AA written budget, written scope of work, workflow diagrams.
  • BA project plan, the system integrator's reputation, detailed budget.
  • CA written implementation plan, design reviews, post-implementation review.
  • DPhone consultations, contract vendor and customer, approved by the customer's CEO.

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    11% (5)
  • C
    83% (38)
  • D
    4% (2)