During the project planning phase, it is essential for the consultant to obtain which one of the following?

The correct answer is D. Documentation of the clients acceptance for each part of the project. See the full explanation below for the reasoning.

Question

During the project planning phase, it is essential for the consultant to obtain which one of the following?

Options

  • AA Gantt chart with all of the correct resources on the project
  • BA work breakdown structure with all of the tasks required
  • CA cultural change document with steps to ensure a smooth transition
  • DDocumentation of the clients acceptance for each part of the project

How the community answered

(35 responses)
  • A
    14% (5)
  • B
    6% (2)
  • C
    3% (1)
  • D
    77% (27)