A change control plan is concerned with all of the following EXCEPT:
The correct answer is C. documenting baseline project plan assumptions. See the full explanation below for the reasoning.
Question
A change control plan is concerned with all of the following EXCEPT:
Options
- Aresponding to the factors that create scope change.
- Bdetermining that a scope change has occurred.
- Cdocumenting baseline project plan assumptions.
- Dmanaging the actual modifications when and if any occur.
How the community answered
(20 responses)- A5% (1)
- B10% (2)
- C85% (17)
Community Discussion