A change control plan is concerned with all of the following EXCEPT:

The correct answer is C. documenting baseline project plan assumptions. See the full explanation below for the reasoning.

Question

A change control plan is concerned with all of the following EXCEPT:

Options

  • Aresponding to the factors that create scope change.
  • Bdetermining that a scope change has occurred.
  • Cdocumenting baseline project plan assumptions.
  • Dmanaging the actual modifications when and if any occur.

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    10% (2)
  • C
    85% (17)