CompTIA
CD0-001 · Question #30
A potential risk to a project could be:
The correct answer is D. allowing scope creep. See the full explanation below for the reasoning.
Question
A potential risk to a project could be:
Options
- Aregular Project Manager meetings.
- Ba risk analysis session.
- Ccreating an assumptions document.
- Dallowing scope creep.
How the community answered
(24 responses)- A4% (1)
- B4% (1)
- C13% (3)
- D79% (19)
Community Discussion
No community discussion yet for this question.