CD0-001 · Question #30

A potential risk to a project could be:

The correct answer is D. allowing scope creep. See the full explanation below for the reasoning.

Question

A potential risk to a project could be:

Options

  • Aregular Project Manager meetings.
  • Ba risk analysis session.
  • Ccreating an assumptions document.
  • Dallowing scope creep.

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    13% (3)
  • D
    79% (19)