CompTIA
CD0-001 · Question #269
In order to prove that a pilot project or proof-of-concept was a success, which of the following is MOST important?
The correct answer is D. Customer acceptance for each item tested has been obtained. See the full explanation below for the reasoning.
Question
In order to prove that a pilot project or proof-of-concept was a success, which of the following is MOST important?
Options
- AThe Chief Executive Officer (CEO) is present and willing to participate in the testing.
- BA complete change order procedure has been established.
- CAll purchase orders are ready to be delivered.
- DCustomer acceptance for each item tested has been obtained.
How the community answered
(41 responses)- A5% (2)
- B10% (4)
- C2% (1)
- D83% (34)
Community Discussion
No community discussion yet for this question.