CompTIA
CD0-001 · Question #264
Once the customer has signed off on the formal requirements documentation, what happens when new requirements are added to the solution if there are no controls in place?
The correct answer is A. Requirements creep. See the full explanation below for the reasoning.
Question
Once the customer has signed off on the formal requirements documentation, what happens when new requirements are added to the solution if there are no controls in place?
Options
- ARequirements creep
- BRequirements renewal
- CRequirements expansion
- DRequirements re-gathering
How the community answered
(46 responses)- A70% (32)
- B15% (7)
- C4% (2)
- D11% (5)
Community Discussion
No community discussion yet for this question.