CompTIA
CD0-001 · Question #245
All of the following are inputs to project schedule development EXCEPT:All of the following are inputs to project schedule development EXCEPT:
The correct answer is A. change requests. See the full explanation below for the reasoning.
Question
All of the following are inputs to project schedule development EXCEPT:All of the following are inputs to project schedule development EXCEPT:
Options
- Achange requests
- Blead- and lag-times.
- Cresource requirements.
- Dresource availability.
How the community answered
(19 responses)- A74% (14)
- B5% (1)
- C5% (1)
- D16% (3)
Community Discussion