All of the following are inputs to project schedule development EXCEPT:All of the following are inputs to project schedule development EXCEPT:

The correct answer is A. change requests. See the full explanation below for the reasoning.

Question

All of the following are inputs to project schedule development EXCEPT:All of the following are inputs to project schedule development EXCEPT:

Options

  • Achange requests
  • Blead- and lag-times.
  • Cresource requirements.
  • Dresource availability.

How the community answered

(19 responses)
  • A
    74% (14)
  • B
    5% (1)
  • C
    5% (1)
  • D
    16% (3)