Question
A finance company receives 10,000 documents per week. 40% of the documents arrive on Tuesday morning. The customer has a five-day work week with seven-hour workdays. Their office space can accommodate only one scanner. What is the minimum effective throughput required for the scanner in order to handle the volume?
Options
- A6 pages per minute (ppm)
- B10 ppm
- C18 ppm
- D22 ppm
How the community answered
(32 responses)- A16% (5)
- B75% (24)
- C3% (1)
- D6% (2)
Community Discussion