A customer wants a comprehensive quote / budget from vendors in response to a Request For Proposal (RFP). The customer wants all elements of the project factored in the quote. What kind of budget…

The correct answer is B. Fixed cost. See the full explanation below for the reasoning.

Question

A customer wants a comprehensive quote / budget from vendors in response to a Request For Proposal (RFP). The customer wants all elements of the project factored in the quote. What kind of budget model is the customer seeking?

Options

  • ATime and materials
  • BFixed cost
  • CMixed cost
  • DTime and materials with cost cap

How the community answered

(51 responses)
  • A
    6% (3)
  • B
    73% (37)
  • C
    16% (8)
  • D
    6% (3)