CD0-001 · Question #228
A company accepts a proposal from a software vendor. The implementation plan objectives should be determined by the:
The correct answer is B. vendor and customer Project Managers. See the full explanation below for the reasoning.
Question
A company accepts a proposal from a software vendor. The implementation plan objectives should be determined by the:
Options
- Asoftware selection team and purchasing department.
- Bvendor and customer Project Managers.
- CChief Information Officer (CIO) and steering committee.
- DIT department.
How the community answered
(23 responses)- A4% (1)
- B74% (17)
- C17% (4)
- D4% (1)