A risk assessment document should be built by:

The correct answer is C. the vendor and customer jointly. See the full explanation below for the reasoning.

Question

A risk assessment document should be built by:

Options

  • Avendor staff then reviewed by the customer.
  • Bcustomer staff then reviewed by the vendor.
  • Cthe vendor and customer jointly.
  • Da non-involved third party.

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    16% (4)
  • C
    72% (18)
  • D
    4% (1)