During the creation of the implementation timeline, consideration should be given to:

The correct answer is B. the availability of resources. See the full explanation below for the reasoning.

Question

During the creation of the implementation timeline, consideration should be given to:

Options

  • Athe project billing date.
  • Bthe availability of resources.
  • Cuser vacation schedules.
  • Dunexpected delays.

How the community answered

(40 responses)
  • A
    8% (3)
  • B
    78% (31)
  • C
    3% (1)
  • D
    13% (5)