A project timeline should take into account all of the following EXCEPT:
The correct answer is A. quarterly quota goals. See the full explanation below for the reasoning.
Question
A project timeline should take into account all of the following EXCEPT:
Options
- Aquarterly quota goals.
- Bcustomer resources availability.
- Chardware ship dates.
- Dimplementation resource availability.
How the community answered
(51 responses)- A78% (40)
- B12% (6)
- C4% (2)
- D6% (3)