CompTIA
CD0-001 · Question #15
A member of the implementation team discovers that the software vendor is issuing a new version. Which one of the following should be done?
The correct answer is D. Notify the Project Manager. See the full explanation below for the reasoning.
Question
A member of the implementation team discovers that the software vendor is issuing a new version. Which one of the following should be done?
Options
- AUpgrade after the project completion date
- BResearch the new product to understand its features
- CInform the business sponsors
- DNotify the Project Manager
How the community answered
(16 responses)- A6% (1)
- B6% (1)
- C13% (2)
- D75% (12)
Community Discussion
No community discussion yet for this question.