Which of the following aspects of the BC/DR process poses a risk to the organization? Response:
The correct answer is D. Full testing of the plan. Full testing of a Business Continuity/Disaster Recovery (BC/DR) plan poses a risk to the organization.
Question
Which of the following aspects of the BC/DR process poses a risk to the organization? Response:
Options
- AThreat intelligence gathering
- BPreplacement of response assets
- CBudgeting for disaster
- DFull testing of the plan
How the community answered
(25 responses)- B4% (1)
- C4% (1)
- D92% (23)
Why each option
Full testing of a Business Continuity/Disaster Recovery (BC/DR) plan poses a risk to the organization.
Threat intelligence gathering is a proactive measure that reduces risk by informing the BC/DR plan.
Preplacement of response assets mitigates risk by ensuring resources are available for quick recovery during a disaster.
Budgeting for disaster is a financial planning activity that reduces risk by allocating necessary resources for recovery.
Full testing of the BC/DR plan inherently carries a risk of disrupting operational systems or services if not executed meticulously, potentially causing downtime or unintended side effects in production environments.
Concept tested: BC/DR testing risks
Source: https://learn.microsoft.com/en-us/azure/architecture/guide/disaster-recovery/dr-testing