Although performing BCDR tests at regular intervals is a best practice to ensure processes and documentation are still relevant and efficient, which of the following represents a reason to conduct a B

The correct answer is B. Application changes. Major application changes necessitate an immediate BCDR review outside of regular intervals, as they directly impact recovery procedures.

Submitted by ngozi_ng· Apr 18, 2026Cloud Security Operations

Question

Although performing BCDR tests at regular intervals is a best practice to ensure processes and documentation are still relevant and efficient, which of the following represents a reason to conduct a BCDR review outside of the regular interval?

Options

  • AStaff changes
  • BApplication changes
  • CRegulatory changes
  • DManagement changes

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    89% (34)
  • C
    3% (1)
  • D
    5% (2)

Why each option

Major application changes necessitate an immediate BCDR review outside of regular intervals, as they directly impact recovery procedures.

AStaff changes

While staff changes are important, they typically require training and documentation updates rather than a full BCDR review, unless key roles in the plan are significantly altered.

BApplication changesCorrect

Changes to critical applications, including new deployments, significant architectural overhauls, or updates to data criticality, can render existing BCDR plans ineffective or obsolete. These changes directly affect the technical steps and resources required for recovery, demanding an immediate review and update of the plan to ensure its continued viability.

CRegulatory changes

Regulatory changes primarily affect policy and compliance aspects; while they might necessitate plan adjustments, they don't impact the technical recovery procedures as directly as application changes.

DManagement changes

Management changes generally affect organizational structure or strategic direction, but not the operational details of how systems are recovered.

Concept tested: BCDR plan review triggers

Source: https://csrc.nist.gov/publications/detail/sp/800-34/rev-1/final

Topics

#BCDR#Disaster Recovery Planning#Business Continuity#Change Management