CCBA · Question #537

A new product that is tablet-enabled is being considered to replace an older product to process orders. The data captured is sent to existing downstream applications, which are not being updated…

The correct answer is D. Identifying constraints and dependencies. The first stepin assessing the impact of a new product is toidentify constraints and dependencies. The BABOK® Guide (Chapter 5.2 - Analyze Current State)recommends that BAs analyzetechnical, business, and regulatory constraintsto ensure compatibility between the new and…

Requirements Analysis and Design Definition

Question

A new product that is tablet-enabled is being considered to replace an older product to process orders. The data captured is sent to existing downstream applications, which are not being updated. What is the first thing that a business analyst (BA) should consider?

Options

  • ADeveloping process and data models
  • BPerforming an interface analysis
  • CConducting a vendor assessment
  • DIdentifying constraints and dependencies

How the community answered

(17 responses)
  • A
    12% (2)
  • B
    6% (1)
  • C
    6% (1)
  • D
    76% (13)

Explanation

The first stepin assessing the impact of a new product is toidentify constraints and dependencies. The BABOK® Guide (Chapter 5.2 - Analyze Current State)recommends that BAs analyzetechnical, business, and regulatory constraintsto ensure compatibility between the new and existing systems. This helps prevent issues such as data format mismatches and system integration failures.

Topics

#constraints and dependencies#system replacement#interface analysis#downstream applications