CCBA · Question #525
A project manager asks a business analyst (BA) to conduct a meeting to walk the stakeholders through how requirements are structured. Which of the following requirement viewpoints will help the BA…
The correct answer is C. Business process model. A Business Process Modelis the most appropriate viewpoint to walk stakeholders through the structure of requirements. It visually represents business processes, the sequence of activities, and how various components interact. This allows stakeholders to understand how…
Question
A project manager asks a business analyst (BA) to conduct a meeting to walk the stakeholders through how requirements are structured. Which of the following requirement viewpoints will help the BA provide that information?
Options
- ABusiness capability analysis
- BData streams
- CBusiness process model
- DState model
How the community answered
(38 responses)- A3% (1)
- B3% (1)
- C89% (34)
- D5% (2)
Explanation
A Business Process Modelis the most appropriate viewpoint to walk stakeholders through the structure of requirements. It visually represents business processes, the sequence of activities, and how various components interact. This allows stakeholders to understand how requirements are structuredand relate to business operations. The BABOK® Guide (Chapter 10.5 - Process Modeling)highlights that business process models help in analyzing process improvements and ensuring stakeholders comprehend the workflows.
Topics
Community Discussion
No community discussion yet for this question.