You need to integrate CA Process Automation with an external application. A data value or status change in the application will result in a CA Process Automation process starting, continuing, or…

The correct answer is D. Send an event to CA Process Automation from the external application when data values or. See the full explanation below for the reasoning.

Question

You need to integrate CA Process Automation with an external application. A data value or status change in the application will result in a CA Process Automation process starting, continuing, or stopping. Which approach enables you to minimize any potential impact on performance?

Options

  • ASend an email into a mailbox monitored by a CA Process Automation mail trigger.
  • BContinuously poll the external application from the CA Process Automation process to ascertain if
  • CContinuously check for a predefined file that the external application will be configured to create in
  • DSend an event to CA Process Automation from the external application when data values or

How the community answered

(24 responses)
  • A
    13% (3)
  • B
    8% (2)
  • C
    4% (1)
  • D
    75% (18)