CA_Technologies
CAT-500 · Question #27
You need to implement failover-safe CA Process Automation touch points. Which CA Process Automation agent deployment guideline should you follow?
The correct answer is C. Use multiple agents deployed on different servers, map these agents to a single touch point, and. See the full explanation below for the reasoning.
Question
You need to implement failover-safe CA Process Automation touch points. Which CA Process Automation agent deployment guideline should you follow?
Options
- AUse a single agent deployed on a powerful hardware platform for each touch point.
- BUse a single agent deployed on a powerful hardware platform and map that agent to multiple
- CUse multiple agents deployed on different servers, map these agents to a single touch point, and
- DUse multiple agents deployed on the same server, map these agents to a single touchpoint, and
How the community answered
(37 responses)- A3% (1)
- B14% (5)
- C78% (29)
- D5% (2)
Community Discussion
No community discussion yet for this question.