Which of the following are the purposes of the Cost-benefit analysis process? Each correct answer represents a complete solution. Choose two.
The correct answer is A. To determine if an investment is sound C. To see how it compares with alternate projects. The Cost-benefit analysis (CBA) process is used to calculate and compare benefits and costs of a project for the following purposes: - To determine if an investment is sound - To see how it compares with alternate projects Answer options D and B are incorrect. These are not the…
Question
Which of the following are the purposes of the Cost-benefit analysis process? Each correct answer represents a complete solution. Choose two.
Options
- ATo determine if an investment is sound
- BTo describe the future value on the investment of the project
- CTo see how it compares with alternate projects
- DTo support benefit management, measurement, and reporting
How the community answered
(24 responses)- A92% (22)
- B4% (1)
- D4% (1)
Explanation
The Cost-benefit analysis (CBA) process is used to calculate and compare benefits and costs of a project for the following purposes: - To determine if an investment is sound - To see how it compares with alternate projects Answer options D and B are incorrect. These are not the purposes of the Cost-benefit analysis