CAS-002 · Question #150
An administrator at a small company replaces servers whenever budget money becomes available. Over the past several years the company has acquired and still uses 20 servers and 50 desktops from five…
The correct answer is B. Increased mean time to failure rate of legacy servers, OS variances, patch availability, and. Piecemeal, unplanned hardware acquisition produces a heterogeneous environment with multiple hardware generations and vendors. The primary risks are: (1) increased mean time to failure (MTTF) as legacy hardware ages and becomes less reliable; (2) OS variances across different…
Question
An administrator at a small company replaces servers whenever budget money becomes available. Over the past several years the company has acquired and still uses 20 servers and 50 desktops from five different computer manufacturers. Which of the following are management challenges and risks associated with this style of technology lifecycle management?
Options
- ADecreased security posture, decommission of outdated hardware, inability to centrally
- BIncreased mean time to failure rate of legacy servers, OS variances, patch availability, and
- COS end-of-support issues, ability to backup data, hardware parts availability, and firmware
- DInability to use virtualization, trusted OS complexities, and multiple patch versions based on
How the community answered
(20 responses)- B85% (17)
- C10% (2)
- D5% (1)
Explanation
Piecemeal, unplanned hardware acquisition produces a heterogeneous environment with multiple hardware generations and vendors. The primary risks are: (1) increased mean time to failure (MTTF) as legacy hardware ages and becomes less reliable; (2) OS variances across different hardware generations requiring different OSes or OS versions; and (3) inconsistent patch availability, since vendors and OS publishers may have ended support for older hardware/OS combinations. These directly reflect the technical and operational risks of an unmanaged technology lifecycle. Options A, C, and D describe some valid issues but are either incomplete, truncated, or less central to the core risks of this specific scenario.