nerdexam
CompTIA

CAS-001 · Question #73

To support a software security initiative business case, a project manager needs to provide a cost benefit analysis. The project manager has asked the security consultant to perform a return on…

The correct answer is D. Nearly three years. Annual savings per project = $50,000 × 30% = $15,000. Total annual savings across 8 projects = $15,000 × 8 = $120,000. Time to recoup the $300,000 investment = $300,000 ÷ $120,000/year = 2.5 years. This rounds to 'nearly three years.' At year 2 only $240,000 has been recovered…

Integration of Computing, Communications and Business Disciplines

Question

To support a software security initiative business case, a project manager needs to provide a cost benefit analysis. The project manager has asked the security consultant to perform a return on investment study. It has been estimated that by spending $300,000 on the software security initiative, a 30% savings in cost will be realized for each project. Based on an average of 8 software projects at a current cost of $50,000 each, how many years will it take to see a positive ROI?

Options

  • ANearly four years
  • BNearly six years
  • CWithin the first year
  • DNearly three years

How the community answered

(16 responses)
  • B
    6% (1)
  • C
    6% (1)
  • D
    88% (14)

Explanation

Annual savings per project = $50,000 × 30% = $15,000. Total annual savings across 8 projects = $15,000 × 8 = $120,000. Time to recoup the $300,000 investment = $300,000 ÷ $120,000/year = 2.5 years. This rounds to 'nearly three years.' At year 2 only $240,000 has been recovered (still a net loss), and at year 3 the cumulative savings reach $360,000, exceeding the initial investment - meaning the ROI becomes positive partway through year 3, making 'nearly three years' the correct characterization.

Topics

#ROI calculation#cost-benefit analysis#security investment#software security initiative

Community Discussion

No community discussion yet for this question.

Full CAS-001 Practice