A new vendor product has been acquired to replace a legacy perimeter security product. There are significant time constraints due to the existing solution nearing end-of-life with no options for…

The correct answer is D. Test the new solution, migrate to the new solution, and decommission the old solution. With time pressure and an end-of-life legacy solution, continuity of security coverage is critical. Option D (Test → Migrate → Decommission) is correct because: testing first validates the new solution works before it is relied upon; migrating while the old system is still…

Technical Integration of Enterprise Components

Question

A new vendor product has been acquired to replace a legacy perimeter security product. There are significant time constraints due to the existing solution nearing end-of-life with no options for extended support. It has been emphasized that only essential activities be performed. Which of the following sequences BEST describes the order of activities when balancing security posture and time constraints?

Options

  • AInstall the new solution, migrate to the new solution, and test the new solution.
  • BPurchase the new solution, test the new solution, and migrate to the new solution.
  • CDecommission the old solution, install the new solution, and test the new solution.
  • DTest the new solution, migrate to the new solution, and decommission the old solution.

How the community answered

(60 responses)
  • A
    3% (2)
  • B
    7% (4)
  • C
    13% (8)
  • D
    77% (46)

Explanation

With time pressure and an end-of-life legacy solution, continuity of security coverage is critical. Option D (Test → Migrate → Decommission) is correct because: testing first validates the new solution works before it is relied upon; migrating while the old system is still technically present ensures no gap in protection; and decommissioning last means the old system provides a fallback during migration. Option A (Install → Migrate → Test) tests after migration - risky because you have already cut over before validating. Option B skips decommissioning entirely. Option C decommissions first, creating a dangerous window with no perimeter protection before the new solution is installed and tested. D preserves security posture throughout the transition.

Topics

#security product migration#change management#perimeter security#risk management