CAS-001 · Question #165
After three vendors submit their requested documentation, the CPO and the SPM can better understand what each vendor does and what solutions that they can provide. But now they want to see the…
The correct answer is B. An RFP. After receiving initial vendor submissions, the CISO should issue an RFP to require vendors to detail exactly how their solutions meet the firm's specific technical and business requirements.
Question
After three vendors submit their requested documentation, the CPO and the SPM can better understand what each vendor does and what solutions that they can provide. But now they want to see the intricacies of how these solutions can adequately match the requirements needed by the firm. Upon the directive of the CPO, the CISO should submit which of the following to the three submitting firms?
Options
- AA T&M contract
- BAn RFP
- CA FFP agreement
- DA new RFQ
How the community answered
(65 responses)- A2% (1)
- B95% (62)
- C3% (2)
Why each option
After receiving initial vendor submissions, the CISO should issue an RFP to require vendors to detail exactly how their solutions meet the firm's specific technical and business requirements.
A T&M (Time and Materials) contract is a billing vehicle defining how a vendor is compensated - it is not a solicitation document used to gather technical solution details from vendors.
An RFP (Request for Proposal) is the correct solicitation document when an organization needs vendors to explain in detail HOW their solution meets specific technical and operational requirements. Unlike an RFQ which focuses solely on pricing, an RFP requests methodologies, architectures, and solution specifics, enabling the CPO and SPM to evaluate technical fit against defined criteria.
An FFP (Firm Fixed Price) agreement is a contract type specifying a fixed deliverable cost - it is a contract form, not a solicitation requesting vendors to demonstrate how their solutions address requirements.
An RFQ (Request for Quotation) solicits only pricing and quantity information and cannot be used to ask vendors to describe the technical intricacies of how their solutions meet specific requirements.
Concept tested: Procurement solicitation documents - RFP vs RFQ