nerdexam
PMIPMI

CAPM · Question #159

CAPM Question #159: Real Exam Question with Answer & Explanation

The correct answer is B: US$120,000. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?

Options

  • AUS$-30,000
  • BUS$120,000
  • CUS$370,000
  • DUS$400,000

Topics

#Earned Value Management#Estimate At Completion#Cost Performance#Forecasting

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions