CAPM · Question #159
A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the…
The correct answer is B. US$120,000. Using the Estimate at Completion (EAC) formula where remaining work is performed at the original planned rate: EAC = AC + (BAC − EV). Solving for EV: EV = AC + BAC − EAC = $150,000 + $220,000 − $250,000 = $120,000. This formula assumes the ETC (Estimate to Complete) equals BAC…
Question
Options
- AUS$-30,000
- BUS$120,000
- CUS$370,000
- DUS$400,000
How the community answered
(40 responses)- A13% (5)
- B78% (31)
- C5% (2)
- D5% (2)
Explanation
Using the Estimate at Completion (EAC) formula where remaining work is performed at the original planned rate: EAC = AC + (BAC − EV). Solving for EV: EV = AC + BAC − EAC = $150,000 + $220,000 − $250,000 = $120,000. This formula assumes the ETC (Estimate to Complete) equals BAC minus EV (i.e., remaining work is done at budget). The result shows the project has earned $120,000 worth of work while spending $150,000, indicating a cost overrun (CPI = 120,000 ÷ 150,000 = 0.8). The other options do not satisfy this formula: −$30,000 (A) and $370,000 (C) and $400,000 (D) are mathematically incorrect.
Topics
Community Discussion
No community discussion yet for this question.