CAP · Question #96
CAP Question #96: Real Exam Question with Answer & Explanation
Sign in or unlock CAP to reveal the answer and full explanation for question #96. The question stem and answer options stay visible for context.
Question
You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?
Options
- A1.06
- B0.93
- C-$37,800
- D0.92
Unlock CAP to see the answer
You've previewed enough free CAP questions. Unlock CAP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.