CAP · Question #305
CAP Question #305: Real Exam Question with Answer & Explanation
The correct answer is B: Resource breakdown structure. See the full explanation below for the reasoning.
Implementation of Security and Privacy Controls
Question
Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create?
Options
- AWork breakdown structure
- BResource breakdown structure
- CRACI chart
- DRoles and responsibility matrix
Topics
#Resource breakdown structure#Project management#Resource planning#Deliverables