CAP · Question #305

CAP Question #305: Real Exam Question with Answer & Explanation

The correct answer is B: Resource breakdown structure. See the full explanation below for the reasoning.

Implementation of Security and Privacy Controls

Question

Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create?

Options

  • AWork breakdown structure
  • BResource breakdown structure
  • CRACI chart
  • DRoles and responsibility matrix

Topics

#Resource breakdown structure#Project management#Resource planning#Deliverables