(ISC)2(ISC)2
CAP · Question #242
CAP Question #242: Real Exam Question with Answer & Explanation
The correct answer is A: Risks. See the full explanation below for the reasoning.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?
Options
- ARisks
- BHuman resource needs
- CQuality control concerns
- DCosts
Topics
#Risk management#Project risk#Fast-tracking#Schedule compression
Community Discussion
No community discussion yet for this question.