CAP · Question #231

Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create?

The correct answer is C. Resource breakdown structure. A Resource Breakdown Structure (RBS) is a hierarchical decomposition of resources-organized by type (human, equipment, materials, etc.)-that shows which resources are assigned to project work. It is presented visually, similar to a WBS, making it exactly what management is…

Implementation of Security and Privacy Controls

Question

Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create?

Options

  • AWork breakdown structure
  • BRoles and responsibility matrix
  • CResource breakdown structure
  • DRACI chart

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    94% (31)

Explanation

A Resource Breakdown Structure (RBS) is a hierarchical decomposition of resources-organized by type (human, equipment, materials, etc.)-that shows which resources are assigned to project work. It is presented visually, similar to a WBS, making it exactly what management is asking for. A Work Breakdown Structure (WBS) decomposes project deliverables into work packages, not resources. A Roles and Responsibility Matrix and RACI chart both map people to tasks/responsibilities, but neither focuses on categorizing the types of resources used across the entire project.

Topics

#Project Management#Resource Management#Project Planning#CAP Concepts