CAP · Question #207
In which of the following phases does the change management process start?
The correct answer is C. Phase 4. In the DITSCAP framework, the change management process formally begins in Phase 4 (Post Accreditation). Once a system is accredited and operating, any subsequent changes to hardware, software, or configuration must go through a structured change management process to ensure the
Question
In which of the following phases does the change management process start?
Options
- APhase 2
- BPhase 1
- CPhase 4
- DPhase 3
How the community answered
(48 responses)- A2% (1)
- B8% (4)
- C85% (41)
- D4% (2)
Explanation
In the DITSCAP framework, the change management process formally begins in Phase 4 (Post Accreditation). Once a system is accredited and operating, any subsequent changes to hardware, software, or configuration must go through a structured change management process to ensure the accreditation remains valid. Phases 1–3 are focused on defining requirements, verifying security, and validating the system for the initial accreditation decision.
Topics
Community Discussion
No community discussion yet for this question.