nerdexam
(ISC)2(ISC)2

CAP · Question #155

CAP Question #155: Real Exam Question with Answer & Explanation

The correct answer is D: Configuration management system. See the full explanation below for the reasoning.

Compliance Maintenance

Question

Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has introduced a scope change request for additional deliverables as part of the project work. What component of the change control system would review the proposed changes' impact on the features and functions of the project's product?

Options

  • ACost change control system
  • BScope change control system
  • CIntegrated change control
  • DConfiguration management system

Topics

#Configuration management#Change control#System integrity#Project management

Community Discussion

No community discussion yet for this question.

Full CAP PracticeBrowse All CAP Questions