CAP · Question #155
Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has…
The correct answer is D. Configuration management system. The configuration management system specifically governs changes to product features and functions, making it the correct component to review scope changes affecting product characteristics.
Question
Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has introduced a scope change request for additional deliverables as part of the project work. What component of the change control system would review the proposed changes' impact on the features and functions of the project's product?
Options
- ACost change control system
- BScope change control system
- CIntegrated change control
- DConfiguration management system
How the community answered
(26 responses)- A4% (1)
- B4% (1)
- C12% (3)
- D81% (21)
Why each option
The configuration management system specifically governs changes to product features and functions, making it the correct component to review scope changes affecting product characteristics.
The cost change control system manages changes that affect the project budget and financial baseline, not the technical features and functions of the product.
The scope change control system manages changes to the project scope baseline defining what work is included, but the configuration management system is specifically responsible for product feature and function integrity.
Integrated change control is the overarching coordination process across all knowledge areas, not a specialized component focused on product technical features and functions.
The configuration management system controls and documents changes to the technical specifications, features, and functions of the project's deliverable or product. When a scope change request introduces additional deliverables or modifies product characteristics, the configuration management system evaluates the technical impact on the established product baseline, ensuring traceability and version control of product features.
Concept tested: Configuration management system and product feature changes
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok