Which of the following statement correct about the shipping point? (Choose two)

The correct answer is B. A shipping point can process the outbound deliveries of several plants C. Several shipping points can be assigned to one plant. See the full explanation below for the reasoning.

Question

Which of the following statement correct about the shipping point? (Choose two)

Options

  • AThe shipping point in the order is determined at order header level
  • BA shipping point can process the outbound deliveries of several plants
  • CSeveral shipping points can be assigned to one plant
  • DWe can assign more than one loading point to a shipping point

How the community answered

(53 responses)
  • A
    8% (4)
  • B
    77% (41)
  • D
    15% (8)