You want to adjust an output in the order-to-cash part of your business. Which of the following do you have to consider when you make the change? (Choose two)
The correct answer is B. The permitted transmission mediums are assigned to the output type in Customizing. D. You must enhance the form that is assigned to the output type if you want to include new document. See the full explanation below for the reasoning.
Question
You want to adjust an output in the order-to-cash part of your business. Which of the following do you have to consider when you make the change? (Choose two)
Options
- AEach output type can have only one transmission medium assigned to it.
- BThe permitted transmission mediums are assigned to the output type in Customizing.
- CThe access sequence of the output determination procedure defines which document data is shown in
- DYou must enhance the form that is assigned to the output type if you want to include new document
How the community answered
(44 responses)- A11% (5)
- B70% (31)
- C18% (8)