SAP
C_TSCM62_65 · Question #81
In which of the following situations is forward scheduling performed at the item level during order entry? Note: There are 2 correct answers to this question.
The correct answer is A. When the available quantity of the material is not sufficient to meet the material availability C. When the transportation planning or material availability date determined by the backward. See the full explanation below for the reasoning.
Question
In which of the following situations is forward scheduling performed at the item level during order entry? Note: There are 2 correct answers to this question.
Options
- AWhen the available quantity of the material is not sufficient to meet the material availability
- BIf the system could not determine a replenishment lead time from the material master.
- CWhen the transportation planning or material availability date determined by the backward
- DWhen the loading date determined by the backward scheduling falls on a public holiday.
How the community answered
(27 responses)- A81% (22)
- B7% (2)
- D11% (3)
Community Discussion
No community discussion yet for this question.