The correct answer is A. The availability check that was carried out included a replenishment lead time in the scope of check.. See the full explanation below for the reasoning.
Question
According to the system there is no stock available, but you still receive a confirmed schedule line in the sales order. What is the reason for this confirmation?
Options
- AThe availability check that was carried out included a replenishment lead time in the scope of check.
- BThe system automatically searches other plants for inventory and transfers this inventory to the plant with
- CThe availability check was carried out, and on saving, the system immediately rescheduled the sales order
- DInventory Management creates a stock transfer when the sales order is saved.
Community Discussion
No community discussion yet for this question.