Which of the following statements regarding the bills of material (BOM) in the sales order are correct? Note: There are 2 correct answers to this question.
The correct answer is B. Bills of material are exploded in the sales document as a structure from the main item and C. Bills of material are defined as master data. The bill of material can be flagged as BOM using. See the full explanation below for the reasoning.
Question
Which of the following statements regarding the bills of material (BOM) in the sales order are correct? Note: There are 2 correct answers to this question.
Options
- AThe sales document type controls whether bills of material relevant to sales are to be
- BBills of material are exploded in the sales document as a structure from the main item and
- CBills of material are defined as master data. The bill of material can be flagged as BOM using
- DThe depth of the explosion of bills of material in the sales document is controlled by specifying
How the community answered
(43 responses)- A19% (8)
- B72% (31)
- D9% (4)