The availability check (ATP) is carried out based on which of the following dates?

The correct answer is A. The material availability date. See the full explanation below for the reasoning.

Question

The availability check (ATP) is carried out based on which of the following dates?

Options

  • AThe material availability date
  • BThe transportation planning date
  • CThe goods issue date
  • DThe loading date

How the community answered

(28 responses)
  • A
    71% (20)
  • B
    18% (5)
  • C
    7% (2)
  • D
    4% (1)