SAP
C_TSCM62_64 · Question #43
The availability check (ATP) is carried out based on which of the following dates?
The correct answer is A. The material availability date. See the full explanation below for the reasoning.
Question
The availability check (ATP) is carried out based on which of the following dates?
Options
- AThe material availability date
- BThe transportation planning date
- CThe goods issue date
- DThe loading date
How the community answered
(28 responses)- A71% (20)
- B18% (5)
- C7% (2)
- D4% (1)
Community Discussion
No community discussion yet for this question.