Which of the following configuration settings is a prerequisite to ensure the explosion of a bill of material in the sales document?
The correct answer is B. The item category of the main item must have the correct settings to allow the explosion of the. See the full explanation below for the reasoning.
Question
Which of the following configuration settings is a prerequisite to ensure the explosion of a bill of material in the sales document?
Options
- AThe schedule line category of the main item must have the correct settings to allow the
- BThe item category of the main item must have the correct settings to allow the explosion of the
- CFor the sub-item components of the bill of material, a suitable item category must be
- DWhen customizing the sales document type, the checkbox Bill of material explosion must be
How the community answered
(50 responses)- A10% (5)
- B82% (41)
- C2% (1)
- D6% (3)
Community Discussion