SAP
C_TSCM52_67 · Question #91
At what level can you set quantity and value updating on a material type?
The correct answer is C. Valuation area. See the full explanation below for the reasoning.
Question
At what level can you set quantity and value updating on a material type?
Options
- APlant
- BCompany code
- CValuation area
- DProcurement type
How the community answered
(16 responses)- B13% (2)
- C81% (13)
- D6% (1)
Community Discussion
No community discussion yet for this question.