SAP
C_TSCM52_67 · Question #9
You want to convert purchase requisition into follow-on documents as easily as possible. What must have been completed successfully in the purchase requisition before you can do this ? Please choose…
The correct answer is A. Source determination. See the full explanation below for the reasoning.
Question
You want to convert purchase requisition into follow-on documents as easily as possible. What must have been completed successfully in the purchase requisition before you can do this ? Please choose the correct answer. Response:
Options
- ASource determination
- BPrice determination
- CMessage determination
- DPartner determination
How the community answered
(62 responses)- A81% (50)
- B5% (3)
- C3% (2)
- D11% (7)