SAP
C_TSCM52_67 · Question #80
You have an open purchase order for a valuated material. What changes can you make to the master data here? (Choose two)
The correct answer is B. Material group in the material master from material group 1 to material group 2 C. Fixed vendor in the source list from vendor A to vendor B. See the full explanation below for the reasoning.
Question
You have an open purchase order for a valuated material. What changes can you make to the master data here? (Choose two)
Options
- AMaterial type from ROH (raw material) to FERT (finished product)
- BMaterial group in the material master from material group 1 to material group 2
- CFixed vendor in the source list from vendor A to vendor B
- DBase unit of measure in the material master from EA (each) to KG (kilogram)
How the community answered
(55 responses)- A9% (5)
- B73% (40)
- D18% (10)
Community Discussion
No community discussion yet for this question.