You have received an order confirmation from a vendor. What do you have to do before you can enter the confirmed delivery date and confirmed quantity in a purchase order item?

The correct answer is C. Use a confirmation control key in the relevant purchase order item. See the full explanation below for the reasoning.

Question

You have received an order confirmation from a vendor. What do you have to do before you can enter the confirmed delivery date and confirmed quantity in a purchase order item?

Options

  • ASet the Goods Receipt indicator.
  • BSet the Confirmation Received indicator in the header.
  • CUse a confirmation control key in the relevant purchase order item.
  • DSet the Acknowledgement Required indicator in the vendor master of the relevant vendor.

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    83% (20)
  • D
    4% (1)