nerdexam
SAP

C_TSCM52_67 · Question #205

For a material subject to split valuation, at which level is the price control moving average set in SAP Materials Management? Please choose the correct answer. Response:

The correct answer is B. Valuation area. See the full explanation below for the reasoning.

Question

For a material subject to split valuation, at which level is the price control moving average set in SAP Materials Management? Please choose the correct answer. Response:

Options

  • AAccount modification
  • BValuation area
  • CValuation group
  • DAccount group

How the community answered

(33 responses)
  • A
    9% (3)
  • B
    82% (27)
  • C
    6% (2)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full C_TSCM52_67 Practice